COMMISSIONING

Six levels. One verifiable handover.

Commissioning is the audit trail that proves your data center will perform under load — from the first design diagram to the day operations takes the keys.

FRAMEWORK

The 6-level commissioning framework

  • L0

    Design & Planning

    Gray Tag

    Reviewing the Owner's Project Requirements (OPR), Basis of Design (BOD), and initial engineering diagrams to catch flaws early.

  • L1

    Factory Acceptance Testing (FAT)

    Red Tag

    Testing critical equipment — generators, UPS systems, chillers — at the manufacturer's facility before it is shipped.

  • L2

    Site Acceptance & Pre-Installation

    Yellow Tag

    Inspecting equipment upon delivery to verify no transit damage occurred and that it matches design specs.

  • L3

    Component Installation & Start-Up

    Green Tag

    Verifying that equipment is installed correctly and safely energizing individual assets for the first time.

  • L4

    Functional Performance Testing

    Blue Tag

    Torture-testing individual systems under simulated full operational loads — often using load banks — to meet performance metrics.

  • L5

    Integrated Systems Testing (IST)

    White Tag

    The 'Black Building' test — the entire data center is stress-tested simultaneously, simulating complete utility power failures.

  • L6

    Closeout, Turnover & Handover

    Black Tag

    Compiling final documentation, training the facility operations team, and officially transferring ownership of the live data center.

Need a commissioning script for a specific level, or a checklist for an upcoming build? We can hand you one in days, not weeks.

Request a callback